Thu
Thu
Thu
Thu

George

Thursday°C
Thu
Thu
Thu
Thu

Wilderness

Thursday°C
Thu
Thu
Thu
Thu

Uniondale

Thursday°C
Thu
Thu
Thu
Thu

Haarlem

Thursday°C

Important numbers

Electricity044 874 3917
Water / Sanitation044 801 9262/9266
Fire 044 801 6311
Refuse Removal044 802 2900
Traffic / Licence044 878 2400 / 044 801 9315
Law Enforcement044 801 6350
GO GEORGE Call Centre0800 044 044
George Municipality Switchboard044 801 9111
Hide -
Published: 20 Feb 2018Title: ELECTRICITY OFF DE SWART LINE 26 FEBRUARY 9AM-4PMStatus: Electricity supply to a portion of De Swart line will be interrupted on MONDAY 26 FEBRUARY 2018 FROM 09:00 TO 16:00 for the purpose of doing alterations to the electrical mains. Please treat the installation as live at all times. Alternative date: Tuesday 27 February 9am-4pm
Published: 20 Feb 2018Title: ELEKTRISITEIT-ONDERBREKING DE SWART LYN 26 FERUARIE 9VM-4NMStatus: Elektriese toevoer sal na De Swart-lyn onderbreek word op MAANDAG 26 FEBRUARIE 2018 VANAF 09:00 TOT 16:00 met die doel om veranderings aan elektriese hoofleidings te maak. Beskou asb installasie as lewendig te alle tyde. Alternatiewe datum: VRYDAG 23 FEBRUARIE 2018 VANAF 09:00 TOT 16:00
Published: 20 Feb 2018Title: ELECTRICITY OFF AIRPORT LINE 23 FEBRUARY 9AM-4PMStatus: Electricity supply to a portion of the Airport line will be interrupted on THURSDAY 22 FEBRUARY 2018 FROM 09:00 TO 16:00 for the purpose of doing alterations to the electrical mains. Please treat the installation as live at all times. Alternative date: 23 February 9am-4pm
Published: 20 Feb 2018Title: KRAGONDERBREKING LUGHAWE-LYN 22 FEBRUARIE 9AM-4NMStatus: Elektriese toevoer na die lughawe-lyn sal onderbreek word op DONDERDAG 22 FEBRUARIE 2018 VANAF 09:00 TOT 16:00 om veranderings aan elektriese hoofleidings te maak. Hanteer as lewendig te alle tye. Alternatiwe datum: 23 Febrarie 9am-4nm.
Published: 12 Feb 2018Title: Black bags: next delivery 26 February - 2 March 2018Status: Distribution of black refuse bags every three months. Each packet contains 26 bags, average of two a week. Please reduce waste and use blue bags for recyclables. Next black bags distributed 26 February-2 March. Blue bags from 82 Meade Street. Every blue bag put out, you get one back. 044 802 2900
5
Home 5Contact usShow

Weather

George
Thursday°C
Thu
Thu
Thu
Thu

Weather

Wilderness
Thursday°C
Thu
Thu
Thu
Thu

Weather

Uniondale
Thursday°C
Thu
Thu
Thu
Thu

Weather

Haarlem
Thursday°C
Thu
Thu
Thu
Thu

Important numbers

Electricity 044 874 3917
Water / Sanitation 044 801 9262/9266
Fire 044 801 6311
Refuse Removal 044 802 2900
Traffic / Licence 044 878 2400 / 044 801 9315
Law Enforcement 044 801 6350
GO GEORGE Call Centre 0800 044 044
George Municipality Switchboard 044 801 9111
11 September 2017

Update on Garden Route Dam Capacity Increase

In 2009 the George Municipality applied for Environmental Authorization to raise the Garden Route Dam spillway by up to 3m in height and to install a Fuse Gate System (FGS) at the point of overflow after it had been  determined that, with the hydrology data available then, this was the most favorable solution for increasing the dam storage capacity. The authorisation for this activity was granted in March 2012. However, the authorised fuse gate alternative  was no longer considered to be the most viable option, following a comprehensive review of the catchment hydrology when the Water Affairs permit was issued in December 2014.

The alternative of constructing a side-channel was investigated to extend the flood overflow length and it was found to be the most effective in raising the dam capacity, while minimizing any future damages risks caused by higher order floods, including those with 1:200 year return periods. This option requires the construction of a concrete spillway wall up to 100 m in length, in a "duckbill" shape in plan, upstream of the existing spillway, and is connected to the existing retaining wall. This design requires the dam wall overflow to be raised by 2,5m and the crest to be raised by 1,8 m to provide sufficient freeboard, to prevent overtopping of the embankment by wave action that may coincide with the occurrence of extreme flood events. The material required to raise the dam wall be sourced from within the dam.  The projected increase to the dam capacity is 25% while the yield increase to the George water supply system would be in the region of 11%.

 

The reconceptualization of the project involved a further tender process for consultants which concluded in January 2017.  The redesign required the Environmental Authorization being reviewed accordingly. Inputs received during the EA process had to be dealt with. In the final design of the project, a dam safety plan had to be drawn up, which was approved by Water Affairs on 22 August 2017.

 

Following administrative and further legal processes as required by the Municipal Supply Chain policy,  the tender for the newly designed project was advertised on 7 September and will close on 9th October 2017.  The supply chain process still requires some prescribed activities which will require several additional weeks prior to the official start of the construction portion of the project, which time cannot be fixed just yet– however it must be noted that this is a long project and which must by special effort be completed by 30th June 2018. The amount budgeted for this project is R12,8 million.

 

Last published 11 September 2017